![]() |
|
| ||
|
Contract: $3,448,000
Design-Build Team Members Engineer: Pennoni Associates Inc. Operator: Enpower Corporation Contractor: Johnston Construction Company Key Accomplishments:
Project Description:
Johnston Construction Company, as general contractor, provided construction and commissioning services under a public-bid, design-bid-build, fixed price contract for the $3.4 million installation of a landfill gas treatment system and flare; filter/chemical feed building including a reverse osmosis water purification system, vacuum belt filter press, and chemical feed skid; landfill gas piping including underground 24-inch HDPE landfill gas main with associated tie-ins to the existing system and large diameter stainless steel gas duct above grade; a bypass road to provide access to existing landfill storage areas during treatment plant during construction; several pile foundations for the treatment equipment and flares; and site utilities, HVAC systems, controls, and electrical facilities. All work was required to be performed with minimal disruption to the existing landfill gas collection system and landfill operations. The landfill gas treatment and flare system consist of a 9,000 scfm, 2-stage Mobile Bed Absorber, Gas Technologies Products, LLC LO-CAT® hydrogen sulfide treatment plant; two John Zink, LLC 4,500 scfm, ultra low emission, LO-NOX® flares; and associated chemical feed and filtration equipment. The landfill gas treatment equipment and flares were procured directly by the Delaware Solid Waste Authority. The LO-NOX® flares which tower over 50 feet into the air are among the largest such flares installed in the United States. Johnston Construction Company has installed a similar flare at the Modern Landfill in York County, Pennsylvania. The LO-CAT® landfill gas treatment plant will treat 9,000 scfm of landfill gas with a maximum of 2,000 ppmv of hydrogen sulfide. The plant includes a sulfur removal capacity of 1 ton per day and hydrogen sulfide removal efficiency up to 99%. After treatment, the landfill gas is sent to Conectiv Power Delivery, where it is converted into electricity. This is only the second landfill gas system of this size in the United States. The other was also installed by Johnston Construction in Warren County, New Jersey. The project was fast-tracked to maximize the Delaware Solid Waste Authority’s return on investment. It was completed in time for the planned operational start-up in July 2007. |