Location41St Street, Ocean City, Maryland 21842
MarketWater Supply and Infrastructure
Contract
$64,121
Team Members
- Owner
- Town of Ocean City
- Prime Contractor
- Johnston Construction Company
Key Accomplishments
- Carried out additional valve-related construction activities within the 41st Street roadway, addressing another component of the municipal water system.
- The project involved work at two distinct valve locations, including an underground vault and a street-level installation area.
- Completed the municipal water infrastructure assignment, which is recorded as complete in Johnston Construction Company's historical project database.
- Johnston Construction Company served as Prime Contractor for the 41st Street Water Valve Project in Ocean City, Maryland, for the Town of Ocean City. The project involved municipal water infrastructure work at two valve locations along 41st Street, including an existing underground valve vault and a separate valve installation within the roadway.
- A primary component of Johnston Construction Company's work involved an existing 12-inch water valve located within an underground vault. The project records identify valve-related work at this location, although the available documentation does not specify whether the activities involved replacement, repair, modification, or other corrective construction procedures.
- The project also included work on another valve situated within the 41st Street roadway. This represented a separate work location from the underground valve vault. The historical project description identifies the additional street valve but does not clearly establish its diameter or the precise nature of the work performed.
- Johnston Construction Company managed the municipal construction assignment under the direction of Project Manager John Lewis, with Charles Mohon identified as Superintendent in the company's historical contact records. The Town of Ocean City served as Owner, with Dean Dashiell identified as the municipal project contact.
- The project records establish that the work began on April 8, 2013, and identify May 17, 2013, as the substantial completion date. The work was classified as a municipal water infrastructure project and is recorded as complete in Johnston Construction Company's historical database.
- Through its participation in the 41st Street project, Johnston Construction Company demonstrated its experience undertaking municipal water infrastructure assignments involving existing valve vaults and roadway water system components.
- The Project Was Completed On May 17, 2013.
Project Description
Johnston Construction Company served as Prime Contractor for municipal water valve work along 41st Street in Ocean City, Maryland, under a time-and-material agreement with the Town of Ocean City.
JCC performed work associated with an existing 12-inch water valve located inside a valve vault.