Markets Served / Project Experience

Central Correctional Facility Collection System Upgrade

Sykesville, Carroll County, Maryland

LocationSykesville, Carroll County, Maryland
MarketWastewater Treatment Plants

Contract

$641,522

Team Members

Owner
Maryland Environmental Service
Engineer
Keystone Engineering Group, Inc.
Prime Contractor
Johnston Construction Company

Key Accomplishments

  • JCC installed approximately 1,400 linear feet of new 12-inch PVC sanitary sewer main.
  • The new gravity sewer was connected to the existing County sewer system through a roadway crossing.
  • The work included five standard sanitary manholes, one internal-drop manhole, and one doghouse manhole.
  • JCC completed modifications, demolition, and abandonment work associated with the existing sewage pumping station.
  • Temporary security fencing was installed to maintain facility security during construction, followed by installation of permanent replacement fencing.
  • The project included excavation, bedding, aggregate backfill, compaction, miscellaneous cast-in-place concrete, and erosion and sediment controls.
  • JCC coordinated traffic management and County-road restoration for the sewer crossing and related construction activities.
  • The work included sanitary-sewer testing, final restoration, project closeout, and turnover documentation.
  • Johnston Construction Company completed the Central Correctional Facility Collection System Upgrade at 7301 Buttercup Road in Sykesville, Maryland.
  • The project was performed under a direct construction agreement with Maryland Environmental Service.
  • The original construction agreement was executed under Contract ID 1-21-2-14-5 and required the work to be substantially completed within 120 calendar days following the Notice to Proceed.
  • The project replaced an outdated sewage pumping station located within the Central Correctional Facility with a new gravity-sewer collection system.

Project Description

Johnston Construction Company completed the Central Correctional Facility Collection System Upgrade for Maryland Environmental Service.

The project replaced an outdated sewage pumping station with a new gravity-sewer collection system serving the correctional facility.