Markets Served / Project Experience

Charles County Pump Station 5A Building Access Modifications

Waldorf, Charles County, Maryland

LocationWaldorf, Charles County, Maryland
MarketPump Stations

Contract details

Johnston Construction Company — Contract
$235,420
B & R Electrical Contractors — Contract
$29,669

Team Members

Owner
Charles County Government – Department of Public Works, Utilities
Engineer
Whitman, Requardt and Associates, LLP
Prime Contractor
Johnston Construction Company

Key Accomplishments

Johnston Construction Company

  • Performed construction at an existing wet well/dry well sewage pumping station while coordinating continued wastewater operations.
  • Completed work around an existing dry-well pumping system located approximately 23 feet below grade.
  • Performed demolition necessary to accommodate the new building-access and process improvements.
  • Installed a new wet well access hatch to improve access to the existing pumping facility.
  • Coordinated structural and architectural modifications associated with the new access improvements.
  • Designed, coordinated and implemented a temporary bypass pumping system so the existing pump station could be taken offline during critical portions of construction.
  • Furnished the labor, equipment, temporary piping, power and maintenance necessary to support temporary pumping operations.
  • Coordinated a bypass system designed around approximately 1,630 gpm at 81.2 feet TDH.
  • Provided a minimum of two duty bypass pumps and one standby pump to maintain wastewater conveyance during construction.
  • Maintained bypass-pumping capability 24 hours per day for the duration required to complete affected work.
  • Used restrained temporary discharge piping and associated supports to reduce the risk of accidental wastewater releases.
  • Coordinated pumping-system monitoring and maintenance to prevent high-level and overflow conditions at the station.

B & R Electrical Contractors

  • Served as the Electrical Subcontractor to Johnston Construction Company for the Pump Station 5A Building Access Modifications project.
  • Furnished the labor, materials, tools and supervision required to perform BRE's electrical scope.
  • Performed electrical demolition associated with the pump-station modifications.
  • Furnished and installed electrical conduit, wire and equipment connections.
  • Installed galvanized rigid conduit (GRC) for exposed electrical work.
  • Installed PVC conduit for underground electrical ductbanks.
  • Performed excavation associated with BRE's underground electrical ductbank work.
  • Installed underground raceways supporting the modified pump-station electrical systems.
  • Installed electrical boxes and devices required for the project.
  • Installed wiring and conductors serving modified and new equipment.
  • Performed instrumentation-related electrical work included within BRE's subcontract.
  • Installed project lighting furnished by Johnston Construction Company.
  • Installed project switchgear furnished by Johnston Construction Company.
  • Coordinated electrical materials supplied by others.

Project Description

Served as Prime Contractor for the comprehensive building-access and process-support improvements at Charles County's existing Pump Station 5A.

Coordinated civil, architectural, mechanical, chemical-feed, electrical and controls work required to complete the modifications.