Markets Served / Project Experience

Dover Long Point Water Treatment Plant Process Improvements

Dover, Kent County, Delaware

LocationDover, Kent County, Delaware
MarketWater Treatment Plants

Contract details

Johnston Construction Company — Contract
$6,592,038
Concrete Services Division — Contract
$216,364
B & R Electrical Contractors — Contract
$795,190

Team Members

Owner
City of Dover
Engineer
AECOM
Prime Contractor
Johnston Construction Company

Key Accomplishments

Johnston Construction Company

  • Renovated the existing water-treatment facility while integrating new treatment processes and infrastructure.
  • Expanded and improved the plant to increase treated-water capacity and enhance the existing treatment process.
  • Constructed new treatment facilities supporting the plant's expanded process operations.
  • Constructed new process tanks associated with backwash and residuals handling.
  • Constructed improvements associated with the new filter building and support tanks.
  • Constructed new backwash processing and residuals facilities.
  • Constructed new GCL-lined sand drying beds for treatment-process residuals handling.
  • Performed subgrade preparation, liner installation and aggregate placement associated with the sand drying beds.
  • Installed sand, rice gravel and pea-gravel media layers associated with the drying-bed system.
  • Coordinated process piping through the sand drying beds and related facilities.
  • Furnished and coordinated a complete automatic pressure-filtration system.
  • Included treatment vessels, inlet distributors/waste collectors, underdrain distributors, support gravel and filtration media as components of the pressure-filtration system.

Concrete Services Division

  • Performed specialized cast-in-place concrete construction supporting a major municipal water treatment plant improvement project.
  • Furnished labor, supervision, formwork-related materials, tools and equipment necessary to execute CSD's concrete scope.
  • Performed concrete work for the Filter Building.
  • Performed concrete work for the Backwash/Residuals Building.
  • Performed concrete work associated with the Sand Drying Beds.
  • Performed concrete improvements associated with renovations to the existing Treatment Building.
  • Mobilized and demobilized concrete equipment, tools and supplies required for the work.
  • Furnished, installed and stripped concrete formwork.
  • Formed footings, slabs-on-grade, straight walls, columns and special concrete elements.
  • Placed concrete for footings, slabs-on-grade, walls, columns and miscellaneous fill applications.
  • Performed concrete finishing, including floating, screeding and machine troweling.
  • Performed point-and-patch finishing to completed concrete surfaces.
  • Performed concrete curing and furnished associated curing supplies.
  • Installed concrete accessories associated with premolded joint material and waterstops.

B & R Electrical Contractors

  • Performed the major electrical construction package for the City of Dover's comprehensive Water Treatment Plant Process Improvements project.
  • Furnished electrical labor, materials, tools, equipment and supervision required to complete BRE's subcontracted work.
  • Installed power conduit, instrumentation conduit, wiring and electrical connections throughout the upgraded treatment facility.
  • Installed electrical infrastructure serving new and renovated water-treatment process equipment.
  • Furnished and installed conduit systems appropriate for interior, exterior, underground and process-area conditions.
  • Installed underground electrical raceways and associated electrical infrastructure.
  • Performed electrical duct-bank excavation associated with the project electrical drawings.
  • Installed wiring and connections for new plant electrical-distribution systems.
  • Performed modifications and demolition involving portions of the plant's existing motor-control-center infrastructure.
  • Furnished and installed work associated with MCC-A, MCC-B and MCC-C.
  • Coordinated startup and training associated with the three motor-control centers.
  • Installed and coordinated electrical distribution equipment serving upgraded process loads.
  • Installed electrical panelboard-related infrastructure serving new and renovated treatment areas.
  • Coordinated new electrical equipment with existing plant distribution systems.

Project Description

Served as Prime Contractor for a comprehensive process upgrade to the City of Dover's Long Point Water Treatment Plant.

Managed a multi-discipline construction program incorporating civil, structural, architectural, mechanical, process, electrical, instrumentation and controls improvements.