LocationEast Berlin, Adams County, Pennsylvania
MarketWater Supply and Infrastructure
Contract
$1,195
Team Members
- Owner
- East Berlin Area Joint Authority
- Subcontractor
- Johnston Construction Company
Key Accomplishments
- Furnished and installed a new flow meter under a purchase order issued by B & R Electrical Contractors, Inc.
- Provided pipefitter labor and installation materials associated with the flow-meter replacement, including documented bolts, gasket kits and restraint components.
- Completed the assignment as part of a formal Water System Improvements project for the East Berlin Area Joint Authority.
- The overall public project was classified as Building/Heavy construction and was subject to Pennsylvania prevailing-wage requirements.
- Coordinated the work with B & R Electrical Contractors, Inc. under the applicable subcontractor insurance, indemnification and prevailing-wage requirements.
- Johnston Construction Company was retained by B & R Electrical Contractors, Inc. to perform a focused portion of the East Berlin Water System Improvements project for the East Berlin Area Joint Authority.
- Available project documentation identifies pipefitter labor together with installation materials including bolts, gasket kits and pipe-restraint components. Detailed technical specifications and drawings for the flow meter are not available, so meter size, manufacturer, electrical requirements, programming, calibration and commissioning procedures are not represented in this project summary.
- The flow-meter replacement supported the East Berlin Area Joint Authority’s broader Water System Improvements program, a public works project subject to Pennsylvania prevailing-wage requirements.
- Johnston Construction Company provided focused flow-meter replacement services supporting the continued operation and improvement of the East Berlin water system while coordinating its work within the requirements of the larger public water-system improvement project.
- The Project Was Completed On .
Project Description
Johnston Construction Company performed subcontracted water-system improvement work associated with the East Berlin Area Joint Authority’s Water System Improvements project.
Removed the existing flow meter serving the East Berlin Well.