Fort Meade Wastewater Treatment Plant Ultraviolet Redundant System

Fort Meade, Maryland

LocationFort Meade, Maryland
MarketWastewater Treatment Plants
DeliveryDesign-Build

Contract details

Johnston Construction Company — Contract
$1,708,693
Electrical Services Division — Contract
$230,208

Design-Build Team Members

Owner
United States Department of Defense / Fort George G. Meade
Prime Contractor
American Water Operations and Maintenance, LLC / American Water Military Services, LLC
Civil Subcontractor
Johnston Construction Company
Engineer
Brian P.E.

Key Accomplishments

Johnston Construction Company

  • The redundant system was designed to treat wastewater flows ranging from approximately 0.5 million gallons per day to a peak flow of 2 million gallons per day.
  • JCC provided six ultraviolet reactors, with one reactor installed on each 12-inch outlet pipe serving the existing sand filters inside the WWTP Filter Building.
  • The reactors were designed for submerged, full-pipe wastewater service and incorporated 316L stainless-steel piping with ANSI 150 flanged connections.
  • Each reactor included variable-power ultraviolet lamps, high-purity quartz sleeves, dry UV-intensity monitors, an automatic low-voltage wiping system, a one-piece wiper ring, temperature sensing, drain and vent connections, and an access hatch.
  • JCC furnished six dedicated free-standing power and control cabinets that provided redundant control capability for the ultraviolet-treatment process.
  • The control cabinets included NEMA 12 enclosures, HMI touchscreens, electronic ballasts, power supplies, microprocessor controls, warning alarms, data logging, remote monitoring, and MODBUS-over-Ethernet communications.
  • Thirty-six molded lamp cables and six sensor and motor cable kits were incorporated into the new equipment installation.
  • JCC furnished and installed six 12-inch isolation valves, allowing individual reactors to be isolated for maintenance and operation without disabling the entire redundant system.
  • Six 2-inch air-release valves were installed, one for each UV reactor, with discharge piping directed to an interior floor drain or sump.
  • The air-release-valve arrangement was coordinated with the reactor manufacturer’s recommended placement upstream and downstream of each reactor.
  • JCC provided the electrical power, conduit, wiring, boxes, fittings, terminations, controls equipment, and associated components required for the new ultraviolet system.
  • Electrical power was extended from the existing motor-control center in the Filter Building through installation of a new MCC bucket and related distribution equipment.

Electrical Services Division

  • Electrical Services Division, LLC performed the electrical construction associated with the new redundant ultraviolet disinfection system at the Fort Meade Wastewater Treatment Plant.
  • The overall design-build project installed six new ultraviolet reactors on the outlet piping from the existing sand filters inside the WWTP Filter Building.
  • The redundant UV system was designed to help maintain continuous effluent disinfection if the existing ultraviolet equipment became unavailable because of electrical failure, controls malfunction, maintenance, or another system interruption.
  • ESD furnished the labor, materials, tools, supervision, conduit, wiring, boxes, devices, switchgear, and electrical connections required for the new UV equipment.
  • The electrical scope included two new 200-amp lighting panelboards serving the redundant ultraviolet system.
  • ESD furnished and installed two new 200-amp motor-control-center buckets to provide power distribution for the six UV equipment panel loads.
  • ESD coordinated the new MCC equipment with the available space and electrical capacity within the existing MCC9 installation.
  • The work included electrical distribution from the existing motor-control center to the new UV power and control cabinets.
  • ESD installed conduit and wiring for the UV equipment, panelboards, control cabinets, and associated electrical loads.
  • The electrical installation included boxes, fittings, devices, terminations, equipment connections, and related accessories necessary for a complete operating system.
  • ESD provided portions of the conduit routing between the UV panels and reactor lamps for smaller instrumentation cables.
  • The work required coordination with the six UV reactors, six power and control cabinets, factory-furnished reactor cables, process piping, valves, and control equipment.
  • ESD coordinated electrical clearances and equipment locations with JCC’s project layout for the UV cabinets, panelboards, and remote telemetry equipment.
  • The project included electrical demolition necessary to accommodate the new distribution and equipment connections.

Additional project details

  • The purpose of the project was to provide redundancy to the wastewater treatment plant’s existing ultraviolet disinfection process.

Project Description

Johnston Construction Company provided design-build services for a redundant ultraviolet disinfection system at the Fort Meade Wastewater Treatment Plant.

The project was developed to maintain continuous effluent disinfection if an electrical failure, controls malfunction, flood event, maintenance activity, or other system issue rendered the existing ultraviolet equipment ineffective.