LocationHagerstown, Washington County, Maryland
MarketWastewater Treatment Plants
DeliveryDesign-Build
Contract details
- Johnston Construction Company — Contract
- $814,732
- Electrical Services Division — Contract
- $58,591
Design-Build Team Members
- Owner
- City of Hagerstown
- Engineer
- GHD, Inc.
- Prime Contractor
- Synagro-WWT, Inc.
- Design-Build Subcontractor
- Johnston Construction Company
Key Accomplishments
Johnston Construction Company
- JCC retained and coordinated GHD, Inc. as its Design Engineer for the engineering portions of the Design-Build scope and participated in initial, 30%, 60% and 90% design workshops with Synagro and the City of Hagerstown.
- Provided final design drawings and specifications along with as-built documentation, equipment information, project scheduling and operations and maintenance documentation as part of the completed Design-Build system.
- Converted the existing digester into an approximately 243,000-gallon sludge storage tank, supporting a two-tank system with approximately 486,000 gallons of total sludge-storage capacity.
- Performed inspection and evaluation of the existing tank to determine the work necessary for conversion to long-term sludge-storage service.
- Cleaned and rehabilitated the existing tank and repaired concrete cracking and spalling where required by the approved Design-Build scope.
- Removed and disposed of the existing tank cover and provided a new aluminum dome-type cover complete with access provisions, ventilation, odor-extraction connections and associated accessories.
- Installed a new sludge aeration and mixing system consisting of two 75 HP positive-displacement blowers, each designed for approximately 1,150 SCFM at 8.3 psig, complete with sound-attenuating enclosures and associated accessories.
- Installed a new stainless-steel coarse-bubble diffuser system within the converted sludge holding tank to provide continuous mixing and aerobic conditions.
- The aeration system incorporated approximately 52 coarse-bubble diffusers, together with manifolds, headers, drop piping, supports and associated structural components.
- Installed associated 8-inch ductile-iron process-air piping, butterfly valves, fittings, supports, wall penetrations, insulation and connection components serving the blower and diffuser systems.
- Core-drilled existing concrete tank walls and installed corrosion-resistant penetration systems incorporating Type 316 stainless-steel components and mechanical link seals.
- Water-blasted and recoated the existing ductile-iron sludge feed and withdrawal piping and replaced associated piping supports as part of the tank conversion.
Electrical Services Division
- Electrical Services Division, LLC served as the Trade Subcontractor supporting Johnston Construction Company’s Design-Build conversion of Secondary Digester No. 2 into an additional sludge holding tank at the Hagerstown Wastewater Treatment Plant.
- Performed the electrical power, control and instrumentation work associated with the new sludge-storage aeration system, including two new 75 HP positive-displacement blowers and their VFD control systems.
- Demolished the existing Panel DGA and installed a new 600A, 480/277V, NEMA 12 power panel, including a 600A main breaker with adjustable trip and dedicated breakers serving the two new blower systems.
- Installed an aluminum equipment backboard in the blower area to support the two VFD blower control panels and associated safety disconnect switches.
- Furnished and installed conduit, conductors and electrical connections to provide 480V power from the new distribution panel to both VFD blower control panels and the two 75 HP blowers.
- Furnished and installed two 100A, 3-pole, NEMA 12 safety switches serving the new blower installations.
- Extended 120V control and auxiliary power to equipment including the blower-enclosure exhaust fans and the sludge-storage level transmitter.
- Installed control wiring between the blower control panels and field devices including differential-pressure switches, high-discharge-pressure switches, high-discharge-temperature switches and motor-winding-temperature switches for both blower systems.
- Provided conduit, wiring and connections from the blower control panels to the plant’s existing PLC for alarm and operating-status interfaces.
- Installed instrumentation wiring between the tank-mounted level sensor and level transmitter for continuous sludge-storage level measurement.
- Provided the 4–20 mA level signal interface from the new level transmitter to the existing PLC, supporting integration of tank-level monitoring into the plant control environment.
- Supported PLC/SCADA integration by providing the field conduit, wiring and signal connections required for blower alarms and tank-level monitoring. PLC and HMI software configuration remained outside ESD's subcontract scope.
- Removed existing conduit and wiring associated with the obsolete mechanical level meter as part of the conversion to the new electronic level-monitoring system.
- Coordinated electrical work with the new mechanical process equipment, blower systems, instrumentation and existing Digester Control Building infrastructure.
Project Description
Johnston Construction Company served as the Design-Build Subcontractor for the conversion of existing Secondary Digester No. 2 into an additional sludge holding tank at the Hagerstown Wastewater Treatment Plant. The project RFP specifically defined the tank conversion as a Design-Build task.
Managed a comprehensive Design-Build delivery process encompassing existing-condition evaluation, engineering coordination, design development, construction management, construction, commissioning and final turnover.