LocationMilford, Delaware
MarketWater Storage and Tanks
Contract details
- Concrete Services Division — Contract
- $43,888
- Electrical Services Division — Contract
- $201,674
Team Members
- Owner
- City of Milford, Delaware
- Engineer
- KCI Technologies Inc.
- Prime Contractor
- Johnston Construction Company
- Subcontractor
- Concrete Services Division, LLC
Key Accomplishments
Concrete Services Division
- Coordinated concrete, testing lab services, concrete pumping services, rental equipment, and jobsite concrete support with Johnston Construction Company.
- Concrete Services Division, LLC performed the concrete construction scope for the Milford Corporate Center Elevated Water Storage Tank project in Milford, Delaware. The overall project included construction of a new single-pedestal 300,000-gallon elevated water storage tank for the City of Milford at the Milford Corporate Center, located at the intersection of Milford-Harrington Highway and Canterbury Road in Kent County, Delaware.
- CSD’s scope included furnishing labor, materials, and tools necessary for forming and concrete placement of the tank foundation in accordance with the project contract documents, selected project drawings, general and special conditions, submittal, quality, execution, construction waste management, cast-in-place concrete, earthwork, and elevated water tank specification sections, along with the CSD control estimate, CB&I project specifications, and CB&I foundation drawings.
- The concrete work included forming, placing, finishing, and curing associated with the tank foundation. CSD’s scope included mobilization and demobilization of concrete equipment, tools, and supplies; rental of form material; purchase of form lumber; installation and stripping of forms; concrete placement labor; concrete finishing labor and supplies; curing labor and supplies; and concrete accessory labor including items such as PMJ, waterstop, caulk, and related concrete accessories.
- CSD also supported specialized foundation work items including footing formwork, slab-on-grade formwork, curved wall formwork, footing placement, slab-on-grade placement, wall placement, float and screed work, trowel finishing, point and patch work, bagging, curing, accessories, mesh, dowels, and pipe pads. This work supported the foundation system required for the new elevated water storage tank structure.
- As part of the project, CSD coordinated concrete purchased by Johnston Construction Company, testing lab services paid for by JCC, concrete pumping services paid for by JCC, and rental of JCC and outside equipment. CSD also included winter protection labor, resteel placing labor and supplies on a time-and-material basis to JCC, unloading rebar labor on a time-and-material basis to JCC, and setting anchor bolts and sleeves on a time-and-material basis to JCC.
- Through this work, Concrete Services Division supported Johnston Construction Company’s construction of the Milford Corporate Center Elevated Water Storage Tank by providing the forming, placement, finishing, curing, accessory installation, and coordination required for the concrete tank foundation.
Electrical Services Division
- Performed electrical construction for a new 300,000-gallon single-pedestal elevated water storage tank serving the Milford Corporate Center area.
- Installed conduit, wiring, lighting, electrical gear, grounding, lightning protection components, handholes, and direct-burial ductbank infrastructure to support tank operation and project completion.
- Coordinated electrical submittals, O&M review, testing services, rental equipment, startup support, and as-built/record drawings for project closeout.
- Electrical Services Division performed the electrical construction scope for the Milford Corporate Center Elevated Water Storage Tank project in Milford, Delaware. The overall project included construction of a new single-pedestal 300,000-gallon elevated water storage tank for the City of Milford, including internal equipment, instrumentation, heating, ventilation, lighting, and wiring associated with the tank improvements.
- The electrical work also included installation of the lightning protection ground ring around the base of the tank, welded tab connections, direct-burial ductbanks, electrical service and light pole ductbank excavation, an electrical handhole, and wire, panel, and conduit labeling. ESD also included six-inch conduits for future antenna cable provisions as part of the project electrical infrastructure.
- ESD coordinated mobilization and demobilization of electrical equipment, tools, and supplies to and from the jobsite. The subcontract scope also included review of required submittals and O&M manuals, coordination of materials provided by others, coordination of testing services, coordination of JCC and outside rental equipment, infrared testing, coordination study, standard testing and startup support, and preparation of as-built/record drawings upon project completion.
- Through this work, Electrical Services Division supported Johnston Construction Company’s completion of the Milford Corporate Center Elevated Water Storage Tank project by providing the electrical systems, lighting, grounding, wiring, and closeout support required for the new municipal water storage facility.
Project Description
Performed concrete forming, placement, finishing, and curing for the tank foundation of a new 300,000-gallon elevated water storage tank.
Supported construction of the elevated water storage tank foundation through footing, slab-on-grade, curved wall, pipe pad, dowel, accessory, and curing work.