Markets Served / Project Experience

Phoenix Resources Landfill – Leachate Concentrator Installation

Wellsboro, Pennsylvania 16901

LocationWellsboro, Pennsylvania 16901
MarketIndustrial and Environmental

Contract

$322,405

Team Members

Owner
Phoenix Resources, Inc. (Waste Management)
Engineer
Somerville, Inc.
Prime Contractor
Johnston Construction Company

Key Accomplishments

  • Furnished and installed new reinforced concrete equipment pads and containment walls, including modifications to the existing concrete load-out area to accommodate additional process equipment and drainage systems.
  • Installed underground dual-contained high-density polyethylene (HDPE) drain piping, consisting of a 3-inch carrier pipe within a 6-inch containment pipe, extending from the new containment area to an existing manhole.
  • JCC furnished and installed new leachate infeed and load-out pumping equipment, including associated valves, fittings, pressure connections, and mechanical accessories.
  • Completed installation of chlorinated polyvinyl chloride (CPVC) process piping associated with the leachate infeed system and concentrate handling facilities, incorporating electrical heat tracing and thermal insulation.
  • Installed a new 2-inch Schedule 40 carbon steel natural gas supply line serving the concentrator flare system, together with associated valves, supports, and piping connections.
  • Coordinated installation of equipment anchor bolts, non-shrink grout, structural supports, and mechanical components associated with the new concentrator equipment and supporting infrastructure.
  • JCC managed electrical and instrumentation construction activities, including power supply connections, conduit, wiring, equipment grounding, and electrical service requirements associated with the concentrator and pumping systems.
  • Performed equipment foundation preparation, piping installation, pump installation, and electrical construction in coordination with the delivery and placement of owner-furnished equipment.
  • Completed construction activities in accordance with Waste Management's site-specific safety requirements and project specifications governing concrete construction, process piping, electrical installations, and mechanical equipment.
  • Johnston Construction Company served as Prime Contractor for the Leachate Concentrator Installation Project at Waste Management's Phoenix Resources Landfill in Wellsboro, Pennsylvania. Under contract with Phoenix Resources, Inc., JCC undertook a comprehensive construction project involving the installation of a refurbished leachate concentrator system, reinforced concrete equipment foundations, containment structures, process piping, pumping equipment, and associated electrical infrastructure.
  • The Project Was Completed On November 14, 2013.

Project Description

Johnston Construction Company served as Prime Contractor for the leachate concentrator installation at Waste Management's Phoenix Resources Landfill in Wellsboro, Pennsylvania, providing comprehensive civil, mechanical, piping, and electrical construction services.

JCC coordinated preparation of the installation area and integration of owner-furnished leachate concentrator equipment, including the concentrator skid, flare skid, duct support structure, and cone-bottom concentrate tank.

Browse all project experience