LocationPreston, Caroline County, Maryland
MarketWastewater Treatment Plants
Contract details
- Johnston Construction Company — Contract
- $9,549,398
- Concrete Services Division — Contract
- $200,089
- B & R Electrical Contractors — Contract
- $567,991
Team Members
- Owner
- Town of Preston
- Design Engineer
- AECOM
- Prime Contractor
- Johnston Construction Company
Key Accomplishments
Johnston Construction Company
- Performed demolition and site modifications required to accommodate the new treatment systems.
- Constructed a new control building supporting the upgraded plant operations.
- Constructed a new influent screening building incorporating below-grade concrete process structures.
- Installed a new influent pumping system to convey wastewater into the upgraded biological treatment process.
- Furnished and coordinated a new programmed aeration treatment system designed for approximately 115,000 gallons per day.
- Constructed a new aeration reactor/pond within the existing lagoon system.
- Performed major earthwork and lagoon-embankment construction associated with the new aeration treatment area.
- Installed a textured geomembrane liner system for the new aeration lagoon.
- Coordinated installation of floating aeration chains, diffuser assemblies and associated process equipment.
- Installed positive-displacement blowers serving the aeration process.
- Incorporated dissolved-oxygen monitoring and automated air-flow control into the aeration system.
- Coordinated VFD-controlled operation of three aeration blowers.
Concrete Services Division
- Served as the concrete subcontractor to Johnston Construction Company for the Preston Wastewater Treatment Plant Upgrade.
- Furnished labor, tools, equipment and supervision for extensive concrete forming, reinforcing, placement and finishing work throughout the treatment facility.
- Performed concrete work associated with the Lagoon No. 1 overflow area, including a concrete pad, yard-hydrant pads and valve-box pads.
- Constructed concrete elements at the influent pump station, including the suction separation wall and associated fillets.
- Completed concrete work for the aerated lagoon, including liner-trench grout, spillway concrete and aerator deadmen.
- Provided grouting associated with the clarifier and RAS/WAS treatment structures as required by the subcontract.
- Constructed extensive reinforced-concrete elements for the barscreen building, including channel slabs, structural walls, beams and fillets.
- Formed and placed barscreen-building foundations, floor slabs, thickened slabs, door stoops and frost walls.
- Constructed equipment pads and the generator-pad slab and frost walls serving the barscreen building.
- Completed structural-concrete construction for the control building, including building footings, slab-on-grade, thickened slabs, door stoops and frost walls.
- Constructed control-building equipment pads and concrete generator-pad components.
- Performed major concrete construction for the filter tank, including bottom and intermediate slabs and multiple reinforced-concrete walls.
- Constructed the filter-tank launder slab, launder wall, stair slabs, stair footings, stairs and stair cheek wall.
- Constructed the grinder pump station anti-flotation pad.
B & R Electrical Contractors
- Performed the major electrical construction scope associated with the comprehensive Preston Wastewater Treatment Plant modernization.
- Furnished the labor, materials, tools, equipment and supervision required for BRE's electrical work.
- Installed conduit, conductors and electrical connections for both power and control systems shown on the project electrical drawings.
- Furnished and installed major electrical distribution equipment serving the new Influent Screen Building.
- Provided the Screen Building's main electrical distribution components, including a 200-amp main breaker.
- Furnished panelboard equipment associated with the Screen Building electrical system.
- Furnished and installed VFD-related equipment serving process equipment at the Screen Building.
- Furnished starter equipment and disconnects required for the Screen Building process loads.
- Installed electrical infrastructure serving wastewater-screening and influent-treatment equipment.
- Furnished and installed major electrical-distribution equipment serving the new Control Building.
- Installed a 400-amp service disconnect for the Control Building.
- Furnished and installed the 400-amp main breaker serving the Control Building electrical system.
- Furnished and installed MCC-A as part of the plant's motor-control infrastructure.
- Furnished a 25 kVA transformer serving required facility loads.
Project Description
Served as Prime Contractor for a comprehensive modernization of the Town of Preston Wastewater Treatment Plant.
Managed construction and renovation of wastewater-treatment buildings, process tanks, lagoons, process piping and associated infrastructure.