Markets Served / Project Experience

Preston Wastewater Treatment Plant Upgrade

Preston, Caroline County, Maryland

LocationPreston, Caroline County, Maryland
MarketWastewater Treatment Plants

Contract details

Johnston Construction Company — Contract
$9,549,398
Concrete Services Division — Contract
$200,089
B & R Electrical Contractors — Contract
$567,991

Team Members

Owner
Town of Preston
Design Engineer
AECOM
Prime Contractor
Johnston Construction Company

Key Accomplishments

Johnston Construction Company

  • Performed demolition and site modifications required to accommodate the new treatment systems.
  • Constructed a new control building supporting the upgraded plant operations.
  • Constructed a new influent screening building incorporating below-grade concrete process structures.
  • Installed a new influent pumping system to convey wastewater into the upgraded biological treatment process.
  • Furnished and coordinated a new programmed aeration treatment system designed for approximately 115,000 gallons per day.
  • Constructed a new aeration reactor/pond within the existing lagoon system.
  • Performed major earthwork and lagoon-embankment construction associated with the new aeration treatment area.
  • Installed a textured geomembrane liner system for the new aeration lagoon.
  • Coordinated installation of floating aeration chains, diffuser assemblies and associated process equipment.
  • Installed positive-displacement blowers serving the aeration process.
  • Incorporated dissolved-oxygen monitoring and automated air-flow control into the aeration system.
  • Coordinated VFD-controlled operation of three aeration blowers.

Concrete Services Division

  • Served as the concrete subcontractor to Johnston Construction Company for the Preston Wastewater Treatment Plant Upgrade.
  • Furnished labor, tools, equipment and supervision for extensive concrete forming, reinforcing, placement and finishing work throughout the treatment facility.
  • Performed concrete work associated with the Lagoon No. 1 overflow area, including a concrete pad, yard-hydrant pads and valve-box pads.
  • Constructed concrete elements at the influent pump station, including the suction separation wall and associated fillets.
  • Completed concrete work for the aerated lagoon, including liner-trench grout, spillway concrete and aerator deadmen.
  • Provided grouting associated with the clarifier and RAS/WAS treatment structures as required by the subcontract.
  • Constructed extensive reinforced-concrete elements for the barscreen building, including channel slabs, structural walls, beams and fillets.
  • Formed and placed barscreen-building foundations, floor slabs, thickened slabs, door stoops and frost walls.
  • Constructed equipment pads and the generator-pad slab and frost walls serving the barscreen building.
  • Completed structural-concrete construction for the control building, including building footings, slab-on-grade, thickened slabs, door stoops and frost walls.
  • Constructed control-building equipment pads and concrete generator-pad components.
  • Performed major concrete construction for the filter tank, including bottom and intermediate slabs and multiple reinforced-concrete walls.
  • Constructed the filter-tank launder slab, launder wall, stair slabs, stair footings, stairs and stair cheek wall.
  • Constructed the grinder pump station anti-flotation pad.

B & R Electrical Contractors

  • Performed the major electrical construction scope associated with the comprehensive Preston Wastewater Treatment Plant modernization.
  • Furnished the labor, materials, tools, equipment and supervision required for BRE's electrical work.
  • Installed conduit, conductors and electrical connections for both power and control systems shown on the project electrical drawings.
  • Furnished and installed major electrical distribution equipment serving the new Influent Screen Building.
  • Provided the Screen Building's main electrical distribution components, including a 200-amp main breaker.
  • Furnished panelboard equipment associated with the Screen Building electrical system.
  • Furnished and installed VFD-related equipment serving process equipment at the Screen Building.
  • Furnished starter equipment and disconnects required for the Screen Building process loads.
  • Installed electrical infrastructure serving wastewater-screening and influent-treatment equipment.
  • Furnished and installed major electrical-distribution equipment serving the new Control Building.
  • Installed a 400-amp service disconnect for the Control Building.
  • Furnished and installed the 400-amp main breaker serving the Control Building electrical system.
  • Furnished and installed MCC-A as part of the plant's motor-control infrastructure.
  • Furnished a 25 kVA transformer serving required facility loads.

Project Description

Served as Prime Contractor for a comprehensive modernization of the Town of Preston Wastewater Treatment Plant.

Managed construction and renovation of wastewater-treatment buildings, process tanks, lagoons, process piping and associated infrastructure.

Browse all project experience