Markets Served / Project Experience

Sussex Shores Water Company – Clearwell 2-2 Installation

Ocean View, Sussex County, Delaware

LocationOcean View, Sussex County, Delaware
MarketWater Storage and Tanks

Contract details

Johnston Construction Company — Contract
$71,764
Concrete Services Division — Contract
$19,953

Team Members

Owner
Sussex Shores Water Company
Engineer
Whitman, Requardt & Associates, LLP
Prime Contractor
Johnston Construction Company

Key Accomplishments

Johnston Construction Company

  • Installed pipework penetrating the clearwell slab and extending approximately five feet beyond the foundation.
  • Coordinated installation of valves, plugs and related water-piping appurtenances.
  • Supplied the crane and rigging required to set the clearwell tank.
  • Coordinated tank setting activities with the tank manufacturer during installation.
  • Performed surveying and layout necessary to establish the correct clearwell location and elevations.
  • Installed the clearwell complete in place in accordance with the project plans, specifications and approved shop drawings.
  • Managed trench support, dewatering, pipe bedding and backfill compaction associated with the underground work.
  • Johnston Construction Company served as the Prime Contractor for the Sussex Shores Water Company Clearwell 2-2 Installation project. The project involved construction of the foundation and installation of a new 50,000-gallon clearwell, including the associated earthwork. The project plans were prepared by Whitman, Requardt & Associates, LLP.
  • JCC’s work included installation of the pipework penetrating the clearwell slab and extending approximately five feet beyond the foundation. This scope included coordination of valves and plugs intended to protect the valves from dirt and debris during construction. JCC was also responsible for supplying the crane and rigging and setting the tank in coordination with the tank manufacturer, as well as performing the surveying necessary to establish the proper location and elevations.
  • The earthwork portion of the project included excavation, protection and refilling of excavations and disposal of excess excavated material associated with the water-main and related work. JCC was also responsible for maintaining excavations free of water through appropriate pumping, drainage or other dewatering measures.
  • Pipeline trenches were excavated to the required widths, depths and grades to provide continuous support for the piping. The specifications also required appropriate trench bracing or sheeting where necessary and controlled backfilling following completion of underground installation.
  • Backfill around the pipelines was required to meet the specified Delaware material requirements. Within road rights-of-way, backfill was mechanically compacted in controlled layers to the specified density, while other trench areas required layered placement and compaction around and above the piping.

Concrete Services Division

  • Furnished the labor, materials, tools and concrete-forming resources required for CSD’s portion of the Clearwell 2-2 construction.
  • Performed concrete forming and placement associated with the new 50,000-gallon clearwell foundation system.
  • Constructed and formed concrete footings required for the clearwell installation.
  • Furnished and installed slab-on-grade formwork.
  • Furnished and installed straight-wall formwork for the project’s concrete wall construction.
  • Installed bulkhead formwork where required by the structural concrete work.
  • Placed concrete for the clearwell tank slab.
  • Placed concrete for wall sections associated with the clearwell foundation.
  • Constructed concrete for two saddle supports serving the clearwell installation.
  • Mobilized and demobilized concrete equipment, tools and supplies required for CSD’s work.
  • Furnished form materials and lumber necessary for the concrete-forming operations.
  • Installed, maintained and stripped concrete forms as construction progressed.
  • Performed concrete finishing operations following placement.
  • Completed floating and screeding of concrete surfaces.

Project Description

Constructed the foundation for a new 50,000-gallon clearwell.

Performed the required excavation, trenching, backfilling and associated earthwork for the installation.