LocationBethany Beach, Sussex County, Delaware
MarketWater Treatment Plants
Contract
$329,390
Team Members
- Owner
- Sussex Shores Water Company
- Engineer
- Hatch Mott MacDonald
- Prime Contractor
- Johnston Construction Company
Key Accomplishments
- Removed the existing flocculation tank and hydropneumatic tank, including associated equipment, concrete bases and supports, and repaired affected building wall openings and surrounding areas.
- JCC coordinated the temporary removal and storage of the existing slat-tray aerators to permit installation of the new aerator discharge piping and pretreatment equipment.
- Replaced the aerator inlet piping and installed the new aerator discharge piping system, including fittings, supports, insulation and heat tracing.
- Installed a new 10-inch in-line mechanical flash mixer and the associated mechanical, electrical and instrumentation components required to integrate the mixer into the treatment process.
- The in-line mixer was designed around an ANCO Series 5000 or approved equal, with Type 316 stainless-steel submerged components, dual counter-acting axial impellers and a minimum ¾ HP drive motor.
- JCC integrated the new in-line mixer with the aeration process controls, with the mixer interlocked to operate whenever the slat-tray aeration blowers were operating.
- Installed new chemical-feed piping for sodium hypochlorite, hydrated lime and polyaluminum-blend treatment chemicals, together with associated support systems and pipe insulation.
- Coordinated chemical piping using corrosion-resistant PVC/CPVC systems, valves and accessories suitable for the applicable chemical service.
- JCC performed the High Service Pump upgrades, including removal of existing pump piping, valves and fittings and reconfiguration of the existing pumping arrangement.
- Removed High Service Pump No. 1 and its existing direct drive, including demolition of the associated pump base and repair of the existing concrete floor.
- Relocated High Service Pump No. 4 to the former Pump No. 1 position and constructed the required new concrete pump pad.
- Removed the existing Pump No. 3 installation and installed a new High Service Pump No. 3, complete with a new concrete equipment foundation and associated piping connections.
Project Description
Johnston Construction Company served as Prime Contractor for the pretreatment improvements at Sussex Shores Water Company’s Water Treatment Plant No. 1 in Bethany Beach, Delaware. The executed contract identifies Sussex Shores Water Company as Owner and Hatch Mott MacDonald as Engineer.
Managed a multi-discipline treatment-plant upgrade encompassing demolition, process piping, high-service pumping, concrete, mechanical equipment, electrical, instrumentation and controls, while coordinating construction within an operating water-treatment facility.