Markets Served / Project Experience

Y&S Candies – MBR Piping And System Tie-Ins

Lancaster, Pennsylvania 17603

LocationLancaster, Pennsylvania 17603
MarketWastewater Treatment Plants

Contract

$187,254

Team Members

Owner
The Hershey Company
Prime Contractor
ADI Systems, Inc.
Civil Subcontractor
Johnston Construction Company

Key Accomplishments

  • Installed a new forward-feed pump, including preparation and placement of the concrete pump foundation, equipment setting, alignment, and associated electrical connections to the existing motor control center.
  • Coordinated installation of process valves, instrumentation, pneumatic air lines, electrical conduit, control wiring, and communication connections required for operation of the expanded wastewater treatment system.
  • The project included modifications to existing treatment equipment, including replacement of a flow-control valve and relocation of an existing 4-inch flowmeter at Continuous Stirred Tank Reactor (CSTR) Digester No. 3, with associated connections to the existing programmable logic controller (PLC).
  • JCC performed upgrades to existing wastewater treatment blowers through installation of new belt drives as part of the mechanical improvements associated with the treatment plant expansion.
  • Installed a new 4-inch stainless steel piping connection between the excess biogas system and the existing flare, incorporating specified pipe routing, slope requirements, and provisions for associated biogas safety equipment.
  • Coordinated installation and integration of ADI-supplied process equipment, valves, instruments, and accessories with contractor-furnished piping, fittings, supports, and installation materials.
  • The construction work included modifications to existing process piping systems, installation of pneumatic valve connections, and electrical and instrumentation interfaces between new equipment and existing control facilities.
  • Supported the expansion of the facility's industrial wastewater treatment infrastructure through coordinated mechanical, piping, civil, electrical, and instrumentation construction activities.
  • Johnston Construction Company performed construction services for the Y&S Candies wastewater pretreatment system expansion in Lancaster, Pennsylvania, for The Hershey Company. Working as Civil Subcontractor under ADI Systems, Inc., the project's Prime Contractor and Design-Builder, JCC was responsible for a construction work package involving membrane bioreactor piping, mechanical equipment installation, process system modifications, and connections to existing wastewater treatment infrastructure.
  • A major component of JCC's work involved fabrication and installation of process piping and system tie-ins associated with the expanded treatment facilities. The construction package incorporated wastewater influent piping, membrane treatment connections, permeate piping, and associated process interfaces. Installation activities required coordination of piping materials, valves, fittings, equipment supports, and connections between new and existing wastewater treatment systems.
  • The project also included installation of a new forward-feed pump serving the wastewater treatment process. Johnston Construction Company's responsibilities included preparation and placement of the concrete pump foundation, setting and alignment of the pumping equipment, and associated piping and electrical connections. Electrical power was supplied from the existing motor control center, requiring coordination of the new equipment installation with the facility's established electrical infrastructure.
  • Modifications to existing treatment facilities included replacement of the flow-control valve at Continuous Stirred Tank Reactor (CSTR) Digester No. 3 with a butterfly valve and relocation of an existing 4-inch flowmeter to the digester discharge piping. The work included associated wiring and connections to the existing programmable logic controller (PLC), allowing the modified mechanical equipment to interface with the facility's process control infrastructure.

Project Description

Johnston Construction Company served as Civil Subcontractor for the wastewater pretreatment system expansion at the Y&S Candies manufacturing facility in Lancaster, Pennsylvania, under ADI Systems, Inc.'s design-build contract.

JCC fabricated and installed process piping and connections associated with the expanded anaerobic membrane bioreactor (AnMBR) treatment system, including wastewater influent, permeate, and associated process piping interfaces.